From a James Pottinger free plan with the October 2004 edition of Model Boats Plywood and Balsa construction Beam = 10in Length = 30in Weight = MOTOR = Electronize 545-12 PROPELLER = Raboesch 3 blade 30mm diameter brass SPEED CONTROL = Electronize FR15HX RUDDER CONTROL = Futaba FP-S148 servo TRANSMITTER = Futaba T6EXA 40MHz RECEIVER = Futaba R136F POWER SUPPLY = Two 6V 3.4Ah lead acid gel batteries
|
![]() |
The plan was carefully photographed using a Canon 300D digital camera. The frames and keel were then edited and drawn in Photoshop, printed on A4 ink jet paper and stuck to the ply with a Prit stick Keel is 6mm ply inner with 6mm Oak stem and Redwood edging and assembled using ZAP epoxy Frames are 1/8th ply Assembly jig on right has slots cut at frame station spacing with the depth adjusted to follow the deck line
|
![]() |
After the 305mm stainless steel prop tube was set in the keel it was assembled with the frames in the jig. Keel parts and assembly jig cut on a table saw, frames with a band saw
|
![]() |
Ready to plank
|
![]() |
Planking is 3mm balsa - medium hard - cut into 6.0mm strips and shaped as required to follow the hull line. All frames and planking set in place with ZAP thin cyano
|
![]() |
23 December 2004 Two layers of glass reinforced plastic have been applied to the hull.
|
![]() |
09 January 2005 Checking layout and C of G.
|
![]() |
12 March 2005 Deck planked in 2mm by 6mm Lime with black card between.
|
![]() |
12 March 2005 Redwood rubbing strips fitted and final coat of polyester resin applied.
|
![]() |
Redwood bulwarks fitted, resin rubbed down and grey primer applied.
|
![]() |
Some of the deck fittings temporarily appled.
|
![]() |
Early stage of detail application, winch from wood, deck light from styrene, companion way from 2mm by 6mm Line, taberbacle from brass sheet.
|
![]() |
Deck house from 0.38mm ply faced with 2mm by 6mm Lime.
|
![]() |
19 March 2005 Floating on the required waterline with no ballast, receiver battery pack in the bow to achieve correct level sit. No Leaks!
|
![]() |
Sailed very well.
|
![]() |
Maiden voyage went on long enough to flatten the receiver battery, so we had to stop, no problems at all.
|
![]() |
Ready for the SWAMBC scale steering competition with 18hrs to spare, we scored a 3rd and a 4th place in the Pilot class.
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
|
![]() |
21 August 2005 |
![]() |
21 August 2005 |
![]() |
21 August 2005 |
![]() |
21 August 2005 |